Unit - 6
Project Monitoring and Control
Key Takeaways:
It is the method of making sure that the mission is constructed according with the necessities of the settlement documents, accepted plans, specifications, constructing codes, constructing code requirements and relevant nearby codes and ordinances.
Key Takeaways:
It does not produce anything but is actively involved in the production process at every step as it supplies raw material, consumable, spare parts to the production department. Store keeping is a service function and the store - keeper acts as a custodian of the material kept in his department.
Key Takeaways:
Periodic Progress Reports outlines the sports you’ve carried out, the duties you’ve completed, and the milestones you’ve reached your mission plan.
1. Write an time table and distribute it beforehand
2. Repeat the objective
3. Review development and destiny moves
4. Stay centered
5. Allow absolutely each person a hazard to talk
6. Avoid boredom
7. Assign moves
8. Summary
Key Takeaways:
Periodic Progress meeting contains:
It involves:
Updating the assignment control software program with real paintings completed
Recording new estimates withinside the software program
Updating the country of play with resources, as an example including in any vacations that a assignment group member is taking so you can correctly agenda their paintings
Entering different facts into the assignment control software program that allows the assignment supervisor to music development and screen the paintings.
How to Update Your Project Schedule-
Resource availability: upload in any excursion time or instances which you realize your crew contributors can’t be to be had for undertaking work
Cost: upload with inside the forecasted and real price of sports.
Key Takeaways:
Updating the assignment control software program with real paintings completed. Recording new estimates with inside the software program. Updating the country of play with resources, as an example including in any vacations that a assignment group member is taking so you can correctly agenda their paintings.
Key Takeaways:
Schedule updating is largely the mission challenge managers perform that pertains to updating the challenge agenda. It involves: Updating the challenge control software program with real paintings completed.
Common causes of time and cost overruns are as follows:
1. Inaccurate Project Estimates
2. Serious Project Design Errors
3. Not Planning for Change Orders
4. Administration Errors
5. Poor Site Management
6. Not Hiring the Right Team
Corrective measures:
Corrective measures are as follows:
1.Pay a variety of interest to undertaking planning
2. Check a vendor’s skills earlier than hiring
3. Attempt to live in the scope that become at first deliberate
4. Use precise scheduling gear & charts
5. Make certain the stakeholders with inside the undertaking are at the equal page
6. Constantly track and degree the development
Key Takeaways:
Common causes are:
Benefits:
Drawbacks:
Key Takeaways:
It is a way of manufacturing aimed toward lowering costs, substances, time and effort. Essentially, the method is to limit the horrific and maximize the good. Using the ideas of lean-production, the preferred final results might be to maximize the fee and output of a mission whilst minimizing wasteful elements and time delay.
Use of Building Information Modelling (BIM) in Project management are as follows:
Key Takeaways:
Quality Control is passed through via way of means of the crew of QC engineers or unique skilled teams. It includes periodic inspection of the development sports and centers if you want to meet the favored standardization as in keeping with the contract.
1. Quality Characteristics
2. Quality of layout
3. Quality of conformance
Key Takeaways:
The objective of concept of quality are:
The first-class in creation pertains to the subsequent objectives:
Key Takeaways:
It’s useful to proportion an in depth best guarantee tick list together along with your provider, even earlier than beginning production. This offers the provider an possibility to check your necessities and notify you if any are unreasonable or want adjusting earlier than mass production.
Key Takeaways:
It is way the checking of cloth or product at numerous tiers of manufacture or production of an item. It is completed with admire to a few pre-described parameters and it attempts to hit upon the defective nature of the item. When we investigate something, we strive to peer the beyond records of production and strive to examine from our beyond experiences.
Potential hazards for workers in construction include:
Hazards & Solutions:
For construction, the 10 OSHA standards most frequently included in the agency's citations in FY 2004 were
Scaffolding:
Hazard
Solutions
Fall Protection:
Hazard
Solutions
Ladders:
Hazard
Solutions
Stairways:
Hazard
Solutions
Trenching:
Hazard
Solutions
Sloping to protect workers by cutting back the trench wall at an angle inclined away from the excavation not steeper than a height/depth ratio of 11 2:1, according to the sloping requirements for the type of soil.
Shoring to protect workers by installing supports to prevent soil movement for trenches that do not exceed 20 feet in depth.
Shielding to protect workers by using trench boxes or other types of supports to prevent soil cave-ins.
Sloping
Cranes:
Hazard
Solutions
Key Takeaways:
Scaffold must be sound, rigid and sufficient to carry its own weight plus four times the maximum intended load without settling or displacement. It must be erected on solid footing. Use safety net systems or personal fall arrest systems (body harnesses).Inspect wire rope, chains and hook for any damage. Know the weight of the load that the crane is to lift.
Causes of accidents:
(1) Unsafe Actions or Acts
(ii) Unsafe Working Conditions
(iii) Personal Causes of Accidents
Preventing measures at the Construction Site:
Preventing measures at the construction Site are as follows:
1. Inspection of Site for Safety :
2. Analysis of each job:
3. Safety education and training:
4. Good Housekeeping:
5. Use of Personal Protective Equipment:
6. Working with machines:
7. Training new recruits:
Key Takeaways:
Preventing accidents at the construction Site are as follows:
For safety and health following things should be done:
1. Make Safety Your Top Priority:
2. Training, Training, and More Training:
3. Get Workers Involved and Invested:
4. Hold Everyone Accountable:
5. Reward the Good, Correct the Bad:
6. Conduct Daily Site Inspections and Safety Meetings:
Key Takeaways:
For safety and health following things should be done:
References:
1. Varghese, P.C.,” Building Construction”, Prentice Hall India,2007.
2. National Building Code, Bureau of Indian Standards,New Delhi,2017.
3. Chudley,R.,Construction Technology,ELBS Publishers,2007.
4. Nunnally,S.W.Construction Methods and Management,Prentice Hall,2006