Unit - 3
Contouring
Q1) What is mean by “Contouring”?
A1)
Fig.: Plan (Contour lines indicate hill)
Fig.: Plan (Contour lines indicate pond)
Q2) What is Contour interval and horizontal equivalent?
A2) Contour interval:
Horizontal equivalents:
Q3) What are the characteristics of contours?
A3)
Fig.: Contour lines of same elevation
Fig.: Intersecting contours in overhanging cliff
(i) When contour lines come close together then it indicates steep slope. Fig. shows steep slope along X-X.
(ii) Uniform slope: if contour lines are equally spaced, uniform slope is indicated.
(iii) A series of straight, parallel and equally spaced contours represent a plane surface.
Fig.: Steep slope along X-X
Fig.: A gentle slope along Y-Y
Fig.: Uniform slope along Z-Z
Fig.: Plane surface slope along P-P
Depression: Closed contour lines with lower values inside indicate a depression.
Fig.: shows depression
Fig.: Shows a hill
Fig. indicates a ridge line. Contour lines cross ridge at right angles. For ridge line the higher elevation contour is inside the loop or band.
Valley line
Fig. indicates a valley line. Contour lines also cross the valley lines at right angles. Valley line is indicated by higher elevation contours outside the loop.
Fig.: Ridge and valley line
Q4) Explain direct method of contouring?
A4)
Procedure:
Fig.: Direct method
(a)The work is started from B.M. and level is setup at the centre of the area.
(b) Suppose it is required to find out the contour of 90.000 m then the staff should be moved to various positions on plot where the reading on staff should give R.L. of 90.000 m. on ground. When all the points are located, they are marked on ground directly.
(c) Similar process is followed for locating the contour of 95.000 m and other contours.
Q5) Explain Indirect method of contouring by cross section?
A5)
Fig.: Method of cross-sections
Q6) Explain Indirect method of contouring by Squares?
A6)
Fig.: Method of square
Q7) Explain Indirect method of contouring by tacheometric method?
A7)
Fig.: Tacheometric method
Q8) Explain Contour gradient?
A8)
Let the RL of the straight point 100.00 m and
Let the distance of the next point 60 m.
B.S on known point is 0.50
HI =100+ 0.50 =100.05 m
Then R1 of the next point =100-(60/30)
=100-2
=98 m
Hence the staff reading =100.50-98