Unit-4
Introduction, shapes and characteristics of wells
Q1) Explain Box caisson and open caisson
A1) (a) Box Caisson
Advantages of Box Caisson
1. Box caisson may be provided just in case alternative sorts prove pricey or don't seem to be possible.
2. It may be extended up to massive depths.
3. It may be created onshore and floated to the place installation.
Disadvantages of Box Caisson
1 It needs exhausting strata for the bearing, therefore appropriate if such stratum is offered at shallow depth.
2 Provision is needed for defense from scouring.
3. Progress is delayed if there's an obstruction like a log or boulders deep down of the caisson.
4. Inspection and excavation deep down is tough and needs different for such work.
5. At bearing strata concrete scale provided might not be satisfied being placed beneath the water.
(b) Open Caisson
Fig. Open Caissons
Advantages of open caissons
1. The caisson may be created to nice depths.
2 the development value is comparatively sawed.
Disadvantages of Open Caisson
1. The clearing and scrutiny of the bottom of the caisson cannot be done
2 Concrete seal placed in water won't be satisfactory.
3. The speed of progress is going to be delayed, if boulders are met throughout the construction.
Q2) Explain pneumatic caisson with advantages and disadvantages.
A2) Pneumatic caisson
Fig Pneumatic caisson
Advantages of pneumatic Caisson
1. Management over the work and preparation of foundation for the sinking of caisson higher since the work is finished within the dry condition.
2 The caisson may be done vertically as careful superintendence is feasible.
3. The bottom of the chamber may be sealed effectively with concrete because it may be placed dry.
4. Obstruction to sinking such as boulders east north east maybe consider.
Disadvantages of gas Caisson
1 Construction value is kind of huge value.
2 The depth of penetration below water is restricted to concerning higher costs are on the far side the endurance of the shape.
Q3) Explain forms of caisson and caisson decease.
A3) Caissons may be completely different shapes
Fig Shapes of Caissons
Circular form
Caisson Diseases
Thereafter only working person is permissible to travel out.
Q4) Explain well foundation with the elements.
A4) The art of good foundation is renowned to Indians well before the sixteen century since world-renowned Taj Mahal stands on the well foundation.
Advantages of Well foundation
COMPONENTS OF WELL FOUNDATION
Cutting edge
Steining
Curb
Concrete seal or bottom plug
Top Plug
Well cap
Cutting Edge
Steining
Curb
Concrete seal or bottom plug
Top Plug
Well cap
The well cap is a control pad to the construction, which can be a pier or associate abutment. It distributes the construction load onto the well steining uniformly.
Fig Components of well foundation
Q5) Explain the forces acting on well foundation.
A5) FORCES ACTING ON WELL FOUNDATION
Dead loads
Live hundred
Impact load
Wind loads
Water pressure
Longitudinal force
Earth pressure
Force
Buoyancy force
Temperature stresses
seismic forces
Resultant force
1. Dead Loads
The weight of the superstructures and the self-weight of the well foundation represent the dead hundreds.
2. Live Loads
The live hundreds within the case of main road bridges are fixed by IRC. For the style of railway bridges, Indian railways follow-
The Indian Railway Bridge Rules (1963) are given by research, style, and Standards Organization (RDSO), Lucknow of the Ministry of Railway, Government of India.
3. Impact loads
The live hundreds cause impact result and it's thought-about within the style of pier cap and bridge seat on the abutment. Impact results could also be neglected for the elements of the well.
4. Wind Loads
Wind loads working on, superstructure and therefore the part of substructure situated higher than the water level are calculated supported "Indian customary Code of following for Structural Safety of Buildings Loading Standard" Wind hundreds act on the exposed space virtually.
5. Water pressure
Water pressure is thanks to the water current working on the part of the substructure between the water level and therefore the maximum scour level.
The intensity of Water pressure on piers parallel to the direction of flow is given by
P = K v 2
Where p = Intensity of Water Pressure (N/m);
V = speed of the water current (m/s).and
K = a constant, that depends upon the form of the well (maximum 788 for sq. over piers, and minimum 237 for piers with cutwaters and case-water)
Vis took to be the most at the free surface of flow and 0 at the deepest scour level, the variation is assumed to be linear. The most worth is taken to be v times the typical worth. A crosswise force of 2 hundredths of that parallel to the flow is assured to permit for occasion obliquity of flow.
6. Longitudinal Force
Longitudinal force happens thanks to rubbing and braking forces. These are transmitted to the substructure in the main through fastened bearing and thru friction on movable bearings per IRC code, a Longitudinal force of W is taken on the free bearing and therefore the balance on the fastened bearing, wherever W is that the total reaction and the constant of friction.
7. Earth Pressure
The earth pressure is calculated supported by one in every of classical earth pressure theories by temperature unit or Coulomb. Passive earth resistance of the soil is taken under consideration for the soundness of foundations below the scour level. The result of the live load on the abutment on the planet pressure is taken into account by taking the constant height of surcharge.
8. Centrifugal force
A force is taken to be transmitted through the bearing the construction is bowed in set up.
9. Buoyancy Force
Buoyancy reduces the effective weight of the well. In masonry or concrete staining 15% of the load is taken the buoyancy force to account for the consistency.
When the well is supported on coarse and, full buoyancy capable the weight of the displaced volume of water is taken into account for semi receptive foundation, the applicable reduction could also be created supported the situation of groundwater level.
10. Temperature Stresses
Longitudinal forces are induced thanks to temperature changes. The movements thanks to temperature changes are partly restrained in beam bridges as a result of friction.
11. Seismic Forces
These are to be considered in an applicable seismic zone. It's capable of a W. wherever W is that the weight of the element, and because of the seismic constant. The worth depends upon the Zone and is given in IS: 1893 1975 Indian customary Criteria of Earthquake Resistance style on Structures"
It is worth ranges from zero.10 0.08. The seismic force acts through the center of gravity of the element. it should act in any one direction at a time. Separate seismic forces are thought-about on the axis of the pier and crosswise to its.
12. Resultant Force
The magnitude, direction, and therefore the purpose of application of all the applicable forces are found for the worst attainable combination. The resultant will be purported to get replaced by constant vertical force W, and lateral forces, P and letter of the alphabet within the longitudinal and crosswise direction of the pier, severally. The action of the letter of the alphabet is going to be additional crucial within the thought of lateral stability of the well.
Q6) Explain the sinking of well.
A6) SINKING OF WELLS
1. Preparatory work
2 Construction of the sand stand
3. Laying of curb
4. Providing shuttering reinforcement and concreting
5. Well staining
6. Measures to increase speed of sinking
1. Preparatory work
Generally, the construction of well foundation commences in the summer season when there is less water in the river. It is economical to locate piers and wells in the dry area since it reduces to some extent the cost of dewatering, timbering, etc. In such case, open excavation upon half a meter above subsoil water level is carried out.
2. Construction of the sand island
At the desired location if the depth of water is less than 5 m, then a sand island is created to facilitate the sinking of well as it is easier to control vertically of well by sand island. The size of the island is adequate to accommodate the well and to have some working area around.
3. Laying of curb
If the depth of water is less than 5 m, the curb is laid on a sand island constructed. However, if it is more, then curt is precast on the store and then floated to site. The cutting curb is supported on wooden sleepers laid on the sand island while the cart is placed below the curbin by one. By providing sleepers a load of curt is distributed uniformly.
Fig Sand island for sinking a well
4. Providing shuttering reinforcement and concreting
Outer stuttering in the form of eel or timber is provident Inner battering content of brick masonry requirement for curb is placed in a position much vertical hand has at least of 2 projections In between shuttering cement concrete of adequate workability is provided without any joint and cured. Thereafter the sleeper below the curb is removed and the well is allowed to sink.
5. Well steining
1.5 m steining constructed and is allowed to sink after attaining sufficient strength. The probability of the well is checked from time to time and suitable connection measures are taken. In the initial stages, steining is cast at a height of 1.5 m and later on, these can be increased to 3 m to overcome frictional resistance.
6. Measures to increase the speed of sinking
For safe and curly sinking of well, the following measurements are taken
Tilting well will cause unequal stresses and the speed of sinking will reduce.
2. By removing the soil uniformly
Vertically speed can be maintained.
3. Jetting of water
Inside and outside the periphery of will reduce frictional resistance this is attained by jetting water through pipes with nozzles all along water periphery.
4. Providing kentledge
Suitable platform resisting on steining is constructed and on this platform kentledge in the form of RSJ /heavy block plates sandbags etc are placed to overcome frictional resistance.
5. Chiseling and Light blasting
In Case, during the sinking of well meets a boulder, which can be taken out by grab or which can obstruct the cutting edge, divers send down and used to call it by ordinary chisels and hammers. This was not successful a hole is to be drilled into the boulder by ordinary chisel und hammer and about I/4 charge (gelignite) is to be deposited is it by divers. The blasting of the charge is to be done electrically from the top of the well with 12 volts battery. This makes the boulder and facilitates the sinking operation.
6. Use of Drop Chisel
When soil strata are hard the excavation operations of the dredger could be aided by the use of a drop chisel The chisel could be just double sections welded together and strengthened by rails co either side of the sections. The chisels should have pointed and at the bottom and a bole sear the top. Through a power winch and steel wire rope, the chisel which may be 3 meters long is held and dropped from a height.
Q7) What do you mean by the tilt of well.
A7) The tilt of the Well
Difficulties in well sinking
Difficulties in well sinking are
During the sinking process of the well, the well can tilt. The magnitude of the tilt that can be allowed is 1 in 60.
The general causes of the tilt of the well
The general causes of the tilt of the wall are
(a) Meeting hand strata such as boulder on one side and soft soil such as sand or weak clay on the other side of the well.
(b) Unequal or eccentric Kentledge.
(c) Slopping bed given tilt p initial stages of sinking operations.
(d) Usual rubbing or excavation inside the dredge hole or outside the well
(e). The sudden sinking of the caisson. The tilt of the well having once started, it is difficult to arrest it when it is occurring we can only rectify the tilt that has occurred.
Usual methods for the rectification of tilt
Methods for the rectification of the tilt
(a) Control of dredging
(b) Packing on the low side
(c) Water Jet method
(d) The method of wedges
(e) Unequal loading
(f) Explosives
(g) Unequal excavation
(a) Control of Dredging
(b) Packing on Low side
(c) Water Jet technique
(d) The methods of Wedges
(e) Unequal Loading
(f) Explosives
Fig Rectification of tilt
(g) Unequal Excavation
Q8) What is sand blowing and tilt of well?
A8) Sand blowing
The shift of the well
Precautions to be determined to stop sand processing tilt and shift
Q9) Explain the retaining wall.
A9) RETAINING WALL
Introduction
Q10) Explain the types of retaining wall.
A10) TYPES OF RETAINING WALLS
Gravity wall
Cantilevered wall
Cantilevered retentive walls area unit made of an interior stem of steel-reinforced, cast-in-place concrete or mortared masonry (often within the form of Associate in inverted T). These walls cantilever hundreds (like a beam) to an outsized, structural footing, changing horizontal pressures from behind the wall to vertical pressures on the bottom below. Typically, cantilevered walls area unit supported on the front, or embrace a counterfort on the rear, to boost their strength resisting high hundreds. Buttress area unit short wing walls at right angles to the most trend of the wall. These walls need rigid concrete footings below seasonal frost depth. This sort of wall uses a lot of less material than a standard gravity wall.
Diaphragm wall
Diaphragm walls area unit a kind of retentive walls that area unit terribly stiff and usually watertight. Diaphragm walls area unit pricy walls, however, they save time and house, and thus area unit utilized in urban constructions.
Sheet pile wall
Sheet pile retentive walls area unit typically utilized in soft soil and tight areas. Pile walls area unit driven into the bottom and area unit composed of a range of fabric together with steel, vinyl, aluminum, covering material or wood planks. For a fast estimate, the fabric is typically driven 1/3 higher than the ground, 2/3 below ground, however, this could be altered reckoning on the setting. Taller pile walls can be like a tie-back anchor, or "dead-man" placed within the soil a distance behind the face of the wall, that's tied to the wall, typically by a cable or a rod. An anchors area unit was then placed behind the potential failure plane within the soil.
Bored pile wall
Bored pile retentive walls area unit designed by grouping a sequence of bored piles, followed by excavating away the surplus soil. Reckoning on the project, the bored pile wall might embrace a series of earth anchors, reinforcing beams, soil improvement operations reinforcement layer. This construction technique tends to be used in eventualities wherever sheath pile could be a valid construction resolution, however wherever the vibration or noise levels generated by a machine aren't acceptable.
Anchored wall
An anchored wall will be made in any of the aforesaid designs however conjointly includes extra strength victimization cables or different stays anchored within the rock or soil behind it. typically driven into the fabric with boring, anchors area unit then expanded at the tip of the cable, either by mechanical suggests that or usually by injecting prestressed concrete, that expands to create a bulb within the soil. Technically advanced, this methodology is incredibly helpful wherever high hundreds area unit expected, or wherever the wall itself must be slender and would preferably be too weak.